THE DIVIDE BLOG


  • November 16, 2015 - 9:25am

    Will Be Ready for Occupany in 2016!!

    The exterior of the Appalachian located on Lot 34 of The Divide is now complete and completely roughed in with paneling being applied inside. Gorgeous home on a gorgeous lot in our civilized wilderness. It does not get better than this and a great value to boot!

  • September 14, 2015 - 10:10am

    We Have a Front Entry

    The front porch has been completed with hand hewn beaming and the roof is closed in ready for shingles. The windows are scheduled to be installed this week and siding installation quickly to follow. Beautiful home with a great view in a fantastic Blue Ridge Mountain community along the Eastern...

  • September 11, 2015 - 10:17am

    We Have a Roof!!!

    Construction on the Appalachian home at The Divide is progressing quickly! The roof is on and insulated. Next, we are planning for the installation of windows and the addition of the front porch. Plumbing and electrical rough-ins are also being completed with interior walls. We are still ahea...

  • August 25, 2015 - 9:04am

    Day 10 Construction

    Lot 34, The Divide. End of the day number 10 for construction of The Appalachian. All trusses and beams in place. Roof tongue and groove being applied. Construction is right on schedule, actually a bit ahead.

  • August 18, 2015 - 3:54am

    Day 5!

    Day 5 of construction on lot 34 The Appalachian. Dormers and gables installed with main hand hewn center beam in place. Most main beam hand hewn rafters installed. Construction at this point is ahead of a very fast schedule. Second floor view is astounding. This is the way cabins used to be ...